News


TOWN OF MAHONE BAY
  • HOME
  • COUNCIL
    • 2026 MUNICIPAL ELECTION
    • MEET COUNCIL
    • BY-LAWS + POLICIES
    • CODE OF CONDUCT
    • CONNECTING WITH COUNCIL
    • NEW COUNCIL AGENDAS, MINUTES + MEETING PACKAGES
    • COMMITTEES
    • TOWN HALL NEWS
    • PLANS, REPORTS + STUDIES
  • TOWN HALL
    • ADMINISTRATION
    • CLIMATE + SUSTAINABILITY
    • DEVELOPMENT + BUILDING
    • EMERGENCY SERVICES
    • EMPLOYMENT OPPORTUNITIES
    • FINANCE
    • FORMS + APPLICATIONS
    • HERITAGE >
      • HERITAGE PROPERTIES
      • TOWN HERITAGE
  • PUBLIC WORKS
    • ASSET MANAGEMENT
    • ELECTRIC UTILITY
    • PARKS + GREENSPACES
    • SOLID WASTE COLLECTION
    • STORMWATER
    • STREETS + ROADS
    • WATER / WASTEWATER
  • CONTACT

Edgewater Project 2025 Year End Update

12/23/2025

 
We’re happy to share an update on the Edgewater Project as we head into winter. While good progress has been made, some parts of the project originally planned for completion in 2025 will move to spring 2026. This change is due to weather conditions, asphalt plant shutdown schedules, and site limitations. The project will remain safe and functional throughout the winter, with final paving and finishing work completed in the spring.

Work Before Close of 2025
Before winter sets in, crews are focused on making Edgewater Street ready for safe driving and snow removal. The team took advantage of recent above-freezing temperatures and base asphalt paving was laid. Catch basins will be adjusted in key areas to reduce winter ponding, and milling work will ensure smoother, plow-friendly transitions. Manholes and valve boxes will be raised to the correct level to avoid damage from snowplows. Concrete work that connects directly to the roadway, such as curb corners and island edges, will also be completed. New street lighting is now energized, and watermain repairs and testing are near completion.

Work Deferred to Spring 2026
Final asphalt paving, including the top lift and trail paving, will take place in spring when temperatures are more suitable. Landscaping and finishing touches, such as topsoil, sod, plantings, benches, picnic areas, and signage, will also be completed at that time. Some concrete work not critical to winter road operations, including certain sidewalks, trail ramps, and park features, will be finalized in spring as well.

What “Spring” Means for This Project
Based on typical construction schedules, asphalt plants usually reopen between late April and mid-May. Weather stability and spring road weight restrictions will also affect timing, but final paving is expected to take place between late April and mid-May, depending on conditions.

Winter Work: January to March 2026
Several important items will continue through the winter where weather allows. This includes completing and commissioning lift stations, finishing storm sewer work behind the Trinity United Church, installing private water and sewer services, and continuing work on fencing, bollards, retaining walls, and small concrete pads. Electrical work will also move forward as equipment becomes available.

Winter Operations and Safety
The base asphalt surface will be fully drivable and plowable throughout the winter. Drainage adjustments will help prevent ponding, and extra care will be taken during snow removal due to the temporary curb height difference until final paving is complete. These measures will help ensure safe travel along Edgewater Street during the colder months.
​
Looking Ahead
The Edgewater Project remains on track for safe winter use. While final paving and landscaping must wait until spring, the roadway will function as intended, with key adjustments in place for winter conditions. We appreciate everyone’s patience and look forward to completing the remaining work between late April and mid-May 2026.

​Should you have comments or questions, please visit the Town's civic engagement site Get On Board Mahone Bay and go to The Edgewater Project, we're happy to hear from you. 

Picture

Comments are closed.

    Archives

    January 2026
    December 2025
    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    May 2020

    Categories

    All
    Budget
    BY LAWS & POLICIES
    BY-LAWS & POLICIES
    COVID 19
    COVID-19
    ELECTION
    FIRE STATION BUILD
    GREEN ENERGY
    NEWS
    PLAN REVIEW
    TRANSPORTATION
    Trees

    RSS Feed

 ADMINISTRATION | COUNCIL | FINANCE  |  ELECTRIC UTILITY  |  EMERGENCY SERVICES |  FORMS + APPLICATIONS | HERITAGE |
PUBLIC WORKS
| STREETS + ROADS
| WASTE COLLECTION SCHEDULE  | ​WATER/WASTE WATER | CONTACT


Town Hall
​493 Main Street, Mahone Bay B0J2E0

Follow us on Social Media for latest News and Updates


Sign Up for Town Hall News Today!

To sign up for our monthly newsletter, send a request email to [email protected]. 

COPYRIGHT © TOWN OF MAHONE BAY 2020. SITE BY SKYSAIL.
  • HOME
  • COUNCIL
    • 2026 MUNICIPAL ELECTION
    • MEET COUNCIL
    • BY-LAWS + POLICIES
    • CODE OF CONDUCT
    • CONNECTING WITH COUNCIL
    • NEW COUNCIL AGENDAS, MINUTES + MEETING PACKAGES
    • COMMITTEES
    • TOWN HALL NEWS
    • PLANS, REPORTS + STUDIES
  • TOWN HALL
    • ADMINISTRATION
    • CLIMATE + SUSTAINABILITY
    • DEVELOPMENT + BUILDING
    • EMERGENCY SERVICES
    • EMPLOYMENT OPPORTUNITIES
    • FINANCE
    • FORMS + APPLICATIONS
    • HERITAGE >
      • HERITAGE PROPERTIES
      • TOWN HERITAGE
  • PUBLIC WORKS
    • ASSET MANAGEMENT
    • ELECTRIC UTILITY
    • PARKS + GREENSPACES
    • SOLID WASTE COLLECTION
    • STORMWATER
    • STREETS + ROADS
    • WATER / WASTEWATER
  • CONTACT